Date:
Thursday, April 17, 2025
Telescope:
CTIO Blanco 4-m
Submitter:
Matthew Penny
Submitter Email:
Observer Support:
Hernan Tirado
Night Assistant:
Alberto Alvarez
Also Present:
Xander Hall,
Problems:
"Major" issue with the mount at 8:05 UT, observing queue stopped. Operator went to the dome to investigate and resolved the issue after 30 min.
Program:
Proposal:
2025A-729671
Target of Oportunity:
No
Time Observed:
10.0
Time Engineering:
0.0
Time lost technical:
0.5
Time lost weather:
0.0
Time lost other:
0.0
Description:
DESI Transient Survey
Primary Investigator:
Palmese
Email:
Institution:
Carnegie-Mellon University
Instrument:
CTIO 4m DECam
Organization:
NOAO
Total Program Time:
10.5
Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
---|---|---|---|---|---|---|
2025-04-17 | 10.0 | 0.0 | 0.5 | 0.0 | 0.0 | 10.5 |
None.