Date:
Wednesday, August 23, 2023
Telescope:
CTIO 1.5-m
Submitter:
Jacqueline Seron
Submitter Email:
Observer Support:
None
Night Assistant:
Jackie Seron
Also Present:
Tim Johns
Problems:
We lost the zero point of the telescope but got it back after the plumb procedure. Poniting was drifting during the night.
Program:
Target of Oportunity:
No
Time Observed:
11.0
Time Engineering:
0.0
Time lost technical:
0.25
Time lost weather:
0.0
Time lost other:
0.0
Primary Investigator:
Todd Henry
Email:
Institution:
SMARTS
Instrument:
CTIO 1.5m Echelle
Organization:
SMARTS
Total Program Time:
11.25
Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
---|---|---|---|---|---|---|
2023-08-23 | 11.0 | 0.0 | 0.25 | 0.0 | 0.0 | 11.25 |
Program completed.
One extra target RKS2123+2457.
Seeing data from DECam.