Date:
Sunday, March 3, 2019
Telescope:
CTIO Blanco 4-m
Submitter:
Bob Blum
Submitter Email:
Observer Support:
Jacqueline Seron
Night Assistant:
Claudio Aguilera
Also Present:
Alistair Walker
Problems:
The observing support staff noted the oil pump was failing and recommended we stop and switch to the spare. This took about 20min. See JIRA.
Program:
Proposal:
2014B-0404
Target of Oportunity:
No
Time Observed:
7.5
Time Engineering:
0.0
Time lost technical:
0.0
Time lost weather:
0.0
Time lost other:
0.0
Description:
DECaLS
Primary Investigator:
Schlegel and Dey
Email:
Institution:
Lawrence Berkeley National Laboratory
Instrument:
CTIO 4m DECam
Organization:
NOAO
Total Program Time:
7.5
Proposal:
2019A-0332
Target of Oportunity:
No
Time Observed:
2.0
Time Engineering:
0.0
Time lost technical:
0.0
Time lost weather:
0.0
Time lost other:
0.0
Description:
Trans Neptune
Primary Investigator:
Sheppard
Institution:
Carnegie Institution of Washington
Instrument:
CTIO 4m DECam
Organization:
NOAO
Total Program Time:
2
| Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
|---|---|---|---|---|---|---|
| 2019-03-03 | 9.5 | 0.0 | 0.0 | 0.0 | 0.0 | 9.5 |
Sheppard and Trujillo for 2.5hr at 1124 local time.