You are here

ENR CTIO Blanco 4-m 2023-02-06

Primary tabs

Date: 
Monday, February 6, 2023
Telescope: 
CTIO Blanco 4-m
Submitter: 
Alistair Walker (1st half), Clara Martínez-Vázquez (2nd half)
Submitter Email: 
Observer Support: 
Manuel Hernandez
Night Assistant: 
Claudio Aguilera
Also Present: 
Marco Bonati
Problems: 

None.

Comments: 

Engineering DECam night.

Running on all the 6  new readout machines. Today we ran 600 zeros + the calibrations.  At the end of this we had a backplane 4 failure.  It did take a SISPI restart to recover.  Marco made some change to the computer and he did capture what the fault was caused by. Everything else looked good, guider and the AOS worked. Several 500s exposures taken through N673, got sub arc sec images perfectly round.

Second half -- good performace of DECam and great seeing. Testing with Science.

Conditions: 
General Conditions
Comment: 
None.
1st Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
1.00
Seeing Variability: 
0.2
Seeing Source: 
The Telescope I used
Sky : 
0
2nd Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
1.00
Seeing Variability: 
0.2
Seeing Source: 
The Telescope I used
Sky: 
0
3rd Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
0.80
Seeing Variability: 
0.2
Seeing Source: 
The Telescope I used
Sky: 
0
4th Quarter
Clouds: 
Clear
Seeing Value: 
0.90
Seeing Variability: 
0.2
Seeing Source: 
The Telescope I used
Sky: 
0
Program: 
Proposal: 
2013A-9999
Target of Oportunity: 
No
Time Observed: 
0.0
Time Engineering: 
8.5
Time lost technical: 
0.0
Time lost weather: 
0.0
Time lost other: 
0.0
Description: 
DECam Engineering
Primary Investigator: 
Walker
Institution: 
CTIO
Instrument: 
CTIO 4m DECam
Total Program Time: 
8.5
Total Times Time Observed Time Engineering Time lost technical Time lost weather Time lost other Total Program Time
2023-02-06 0.0 8.5 0.0 0.0 0.0 8.5