Date:
Monday, May 10, 2021
Telescope:
CTIO Blanco 4-m
Submitter:
Larissa Markwardt
Submitter Email:
Observer Support:
Alberto Alvarez
Night Assistant:
Hernan Tirado
Problems:
Around 8 pm local time, SISPI crashed due to the DECAL computer, but we lost almost no time.
Program:
Proposal:
2019A-0337
Target of Oportunity:
No
Time Observed:
11.75
Time Engineering:
0.0
Time lost technical:
0.25
Time lost weather:
0.0
Time lost other:
0.0
Description:
The Deep DECam Outer Solar System Survey (DDOSSS)
Primary Investigator:
David Trilling
Email:
Institution:
Northern Arizona University
Instrument:
CTIO 4m DECam
Organization:
NOAO
Total Program Time:
12
| Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
|---|---|---|---|---|---|---|
| 2021-05-10 | 11.75 | 0.0 | 0.25 | 0.0 | 0.0 | 12 |
None.