Date:
Monday, April 26, 2021
Telescope:
CTIO Blanco 4-m
Submitter:
Melissa Graham
Submitter Email:
Observer Support:
Alfredo Zenteno
Night Assistant:
Hernan Tirado
Also Present:
Alberto Alvarez
Problems:
Power failure at dome meant system required reboot during the first quarter of the night.
Program:
Proposal:
2021A-0113
Target of Oportunity:
No
Time Observed:
10.5
Time Engineering:
0.0
Time lost technical:
0.0
Time lost weather:
0.0
Time lost other:
0.0
Description:
DECam Alliance for Transients
Primary Investigator:
M Graham
Email:
Institution:
University of Washington
Instrument:
CTIO 4m DECam
Organization:
NOAO
Total Program Time:
10.5
| Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
|---|---|---|---|---|---|---|
| 2021-04-26 | 10.5 | 0.0 | 0.0 | 0.0 | 0.0 | 10.5 |