Date:
Sunday, August 16, 2015
Telescope:
CTIO Blanco 4-m
Submitter:
Jim Annis
Submitter Email:
Observer Support:
None
Night Assistant:
Alberto Alvarez
Also Present:
Leonardo Paredes
Problems:
SISPI hung during our morning twilight standards. We had to reboot SISPI to recover. Unclear what the problem was: it looked like SISPI was waiting for the telescope position.
Program:
Proposal:
2015B-0265
Target of Oportunity:
No
Time Observed:
0.5
Time Engineering:
0.0
Time lost technical:
0.0
Time lost weather:
5.0
Time lost other:
0.0
Description:
The Inner Oort Cloud Population
Primary Investigator:
Scott Sheppard
Email:
Institution:
Carnegie
Instrument:
CTIO 4m DECam
Total Program Time:
5.5
Proposal:
2012B-0001
Target of Oportunity:
No
Time Observed:
5.0
Time Engineering:
0.0
Time lost technical:
0.0
Time lost weather:
0.0
Time lost other:
0.0
Description:
The Dark Energy Survey
Primary Investigator:
Josh Frieman
Email:
Institution:
Fermilab
Instrument:
CTIO 4m Mosaic
Total Program Time:
5
Total Times | Time Observed | Time Engineering | Time lost technical | Time lost weather | Time lost other | Total Program Time |
---|---|---|---|---|---|---|
2015-08-16 | 5.5 | 0.0 | 0.0 | 5.0 | 0.0 | 10.5 |
None.