Problems: 

Generator failed in the afternoon; fixed by the hard work of CTIO staff and we were up and running a bit after sunset - no observing time was lost. Two frames (430271 and 430292) did not get written to disk since two Image Builders failed. Ran all night with the remaining 3 without any problems. Hopefully these will be recovered ...? All environmental readouts were down - hopefully fixed by tomorrow night? SISPI kept complaining that the Alarm History and Interlock Viewer pages were unresponsive. Observer console had to be refreshed ~3 times through the night. TCS communication with SISPI failed at UT 06:36; after some fiddling - restarted SISPI at 06:53. Lost ~30 min at end of night. We tried to restart SISPI, but could not bring up any of the GUI windows using the DECam icon. Starting an observer console from a browser did not give us any functionality. Klaus realized that decal was down; Claudio rebooted; see e-mail notes. I took some test frames, so system seems to be working.

Comments: 

Good night; z-band seeing of 0.85 - 1.2 during the first half; 1.0-1.5-1.0 during the second half.  Used only z-band tonight. Lost ~30 min at the end of the night.

Conditions: 
General Conditions
Comment: 
None.
1st Quarter
Clouds: 
Clear
Seeing Value: 
1.00
Seeing Variability: 
0
Seeing Source: 
The Telescope I used
Sky : 
0
2nd Quarter
Clouds: 
Clear
Seeing Value: 
0.00
Seeing Variability: 
0.2
Seeing Source: 
CTIO Seeing monitor
Sky: 
0
3rd Quarter
Clouds: 
Clear
Seeing Value: 
1.30
Seeing Variability: 
0
Seeing Source: 
The Telescope I used
Sky: 
0
4th Quarter
Clouds: 
Clear
Seeing Value: 
1.00
Seeing Variability: 
0
Seeing Source: 
The Telescope I used
Sky: 
0
Program: 
Proposal: 
2014B-0404
Target of Oportunity: 
No
Time Observed: 
10.0
Time Engineering: 
0.0
Time lost technical: 
0.5
Time lost weather: 
0.0
Time lost other: 
0.0
Description: 
DECaLS: DECam Legacy Survey
Primary Investigator: 
Schlegel and Dey
Institution: 
NOAO
Instrument: 
CTIO 4m DECam
Organization: 
NOAO
Total Program Time: 
10.5
Total Times Time Observed Time Engineering Time lost technical Time lost weather Time lost other Total Program Time
2015-04-07 10.0 0.0 0.5 0.0 0.0 10.5