You are here

ENR CTIO 1.5-m 2020-02-29

Primary tabs

Date: 
Saturday, February 29, 2020
Telescope: 
CTIO 1.5-m
Submitter: 
Roberto Aviles
Submitter Email: 
Observer Support: 
None
Night Assistant: 
None
Problems: 
None.
Comments: 

The program was completed successfully.

1st quarter of night, DIMM down.

07:12 UT Fails to go to "11596" TCS reports LIMITS and disabled dome. It was inside allowed limits. OK in second try.

08:18 UT Fails to reach GJ0618B, stops in DEC, OK in 2nd try.

Conditions: 
General Conditions
Comment: 
None.
1st Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
0.00
Seeing Variability: 
0
Seeing Source: 
CTIO Seeing monitor
Sky : 
0
2nd Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
0.70
Seeing Variability: 
0.2
Seeing Source: 
CTIO Seeing monitor
Sky: 
0
3rd Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
0.80
Seeing Variability: 
0.2
Seeing Source: 
CTIO Seeing monitor
Sky: 
0
4th Quarter
Clouds: 
Clear
Wind: 
Low
Seeing Value: 
0.90
Seeing Variability: 
0.2
Seeing Source: 
CTIO Seeing monitor
Sky: 
0
Program: 
Proposal: 
K Kids
Target of Oportunity: 
No
Time Observed: 
9.75
Time Engineering: 
0.0
Time lost technical: 
0.0
Time lost weather: 
0.0
Time lost other: 
0.0
Primary Investigator: 
Todd Henry
Institution: 
SMARTS
Instrument: 
CTIO 1.5m Echelle
Organization: 
SMARTS
Total Program Time: 
9.75
Total Times Time Observed Time Engineering Time lost technical Time lost weather Time lost other Total Program Time
2020-02-29 9.75 0.0 0.0 0.0 0.0 9.75